GAZETTE NOTICE NO. 3495 of 1st April 2011

KIAMBERE-MWINGI WATER AND SANITATION COMPANY

Tariff Structure for the year
1st January 2011 to 30th June 2013
Tariff Structure

Water Tarrif Structure

Customer CategoryApproved/ Justified Tariff (Ksh/m3)
Residential Household
0-6Fixed Charge Ksh.530
7-20135
21-50182
51-100232
100-300300
300->403
Commercial/Industrial
0-6Fixed Charge Ksh.590
7-20145
21-50192
51-100242
100-300310
300->413
Government Institutions
0-6Fixed Charge Ksh.530
7-20135
21-50182
51-100232
100-300300
300->403
Schools and Colleges
0-600Fixed Charge Ksh.148.5
601-1200225
1200->292
Water Kiosks
Per-M3Fixed Charge Ksh.130
Resale at Water Kiosk
Per-20 LitresFixed Charge Ksh.4

 

Sewer Tarrif Structure

No sewer

Meter Rents

Meter Rent per Month

Size (inches)Approved Charge (Ksh.)
inches50
inches50
1 inches250
1 inches250
2 inches250
3 inches450
4 inches800
5 inches1500
6 inches1500
Over 6 inches2000



Water Deposits

Water Deposits

Connection TypeApproved Charge (Ksh.)
Domestic2000.00
Retail shops consuming more than 10m35000.00
Bar, restaurant and lodgings more than 15m35000.00
Hotel class A and B less than 150m310000.00
Hotel class C and D more than 150m320000.00
Hospitals more than 150m320000.00
Health Centres less than 150m310000.00
Schools and other institutions more than 200m320000.00
Schools less than 200m310000.00
Minor construction less than 200m315000.00
Major construction sites more than 200m350000.00
Light industries less than 200m330000.00
Medium industries 200 to 300m350000.00
Heavy industries more than 300m3100000.00



Other Charges

Other Charges

Service DescriptionApproved Charge (Ksh.)
For cutting off the supply at the request of the consumer500
For turning on supply as a first connection35% of cost of materials
For turning on the supply otherwise than as a first connection500.00
For turning on the supply after a disconnection for non- payment500.00 and double deposit for every default up to a maximum 2.5 times of your bill
Meter testing fee500.00
Penalty for irregular connection- domestic15,000.00 and double deposit
Penalty for irregular connection- Commercial/ Industrial30,000.00 and double deposit
For cutting off the supply at the request of the consumer500
For turning on supply as a first connection35% of cost of materials
For turning on the supply otherwise than as a first connection500.00
Meter testing fee500.00



Penalties

Penalties

Penalty DescriptionApproved Charge (Ksh.)
For turning on the supply after a disconnection for non- payment500.00 and double deposit for every default up to a maximum 2.5 times of your bill
Penalty for irregular connection- domestic15,000.00 and double deposit
Penalty for irregular connection- Commercial/ Industrial30,000.00 and double deposit